The European Parliament granted budget approval (discharge) for the 2014 ITER fusion energy project after initially delaying it due to massive cost increases and significant delays. 8 08.12.2016
Other
energy
budget
science
finance
public administration
research and intellectual property
Key points
- The European Parliament formally granted discharge for the 2014 budget of the ITER Joint Undertaking in October 2016.
- The project faced significant financial risks, with construction phase costs rising to approximately €6.6 billion.
- A major delay of at least 43 months was identified in the construction schedule of the project.
- The 2014 budget included commitment appropriations of €1,168.8 million and payment appropriations of approximately €576.6 million.
Documents (PDFs)
SECOND REPORT on discharge in respect of the implementation of the budget of the European Joint Undertaking for ITER and the Development of Fusion Energy for the financial year 2014
REPORT on discharge in respect of the implementation of the budget of the European Joint Undertaking for ITER and the Development of Fusion Energy for the financial year 2014
Discharge 2014: Joint Undertaking for ITER and the Development of Fusion Energy
Discharge 2014: Joint Undertaking for ITER and the Development of Fusion Energy
These raw data are provided by the Open Data Portal of the European Union (data.europa.eu) and are licensed under ODC-BY 1.0.